Old K-10 Road Work

Old K10 Road to Spring Creek roadwork will begin September 1st. A full depth reclamation with cement will be followed by a double chip seal. The reclamation will take about 2-3 weeks and the chip seal about 1 week. The reclamation will cover about 1/2 mile per day. Expect delays or detours in these work areas daily.

Here is a link with information on full depth reclamation.

Thank You

Wabaunsee County Road & Bridge